Project Management Professional (PMP) Exam Practice – Question0879

A project manager assumes a three-year, multiphase project with tight timelines. Stakeholder schedules permit time for addressing only essential activities
How should the project manager handle updating the lessons learned?


A.
Schedule lessons learned meetings at the end of each phase.
B. Wait to gather lessons learned until the end of each year.
C. Periodically seek feedback on lessons learned.
D. Fast track the project by gathering lessons learned only at the end of the project.

Correct Answer: A