A project manager discovers an enhancement that will improve the design being developed by a subject matter expert (SME). What should the project manager do?
A. Document this discovery, and present it to all stakeholders.
B. Ask the expert to implement the enhancement.
C. Disregard the enhancement, as no changes are allowed.
D. Ask the change control board (CCB) to review the enhancement.
A. Document this discovery, and present it to all stakeholders.
B. Ask the expert to implement the enhancement.
C. Disregard the enhancement, as no changes are allowed.
D. Ask the change control board (CCB) to review the enhancement.