Project Management Professional (PMP) Exam Practice – Question0883

The change control board (CCB) authorizes two corrective actions for implementation. The first action will cause a delay in delivering the regular stakeholder communication report. The second action will require more man hours on a severely delayed task on a
critical path.
What should the project manager do first?


A.
Implement the first corrective action, since it was received first.
B. Hire an additional resource so that both corrective actions can be implemented simultaneously.
C. Implement the second corrective action, since it is on a critical path.
D. Ask the CCB for further clarification on its expectations.

Correct Answer: D