Project Management Professional (PMP) Exam Practice – Question0884

A project manager realizes that an issue that occurred several weeks ago has negatively impacted the schedule. When the mitigation plan is initiated, it fails because the required resources are now unavailable.
What should the project manager have done to avoid this?


A.
Conducted stand-up meetings to communicate project status
B. Sent out status reports to stakeholders
C. Reviewed and updated the risk mitigation plan
D. Updated the resource management plan

Correct Answer: C