Project Management Professional (PMP) Exam Practice – Question0887

A project manager is managing a new client. The project requires knowledge of upcoming technologies, but existing team members have no experience working with these technologies.
What should the project manager do to engage the team in work relating to these technologies?


A.
Ask team members to individually learn the technologies.
B. Organize internal and external training for all team members on the technologies.
C. Hire a technical expert on the technologies.
D. Replace the existing resources with new ones that have knowledge of these technologies.

Correct Answer: B