Project Management Professional (PMP) Exam Practice – Question0888

A recently promoted project manager must facilitate the weekly status update meeting. What should the project manager do to ensure a productive meeting?


A.
Carefully read the latest meeting minutes.
B. Avoid or smooth over any disagreements.
C. Limit attendance to the project team and stakeholders.
D. Circulate a defined agenda in advance.

Correct Answer: D