Project Management Professional (PMP) Exam Practice – Question0889

A project team member begins working on a customer-requested task that is critical to project success. However, this task is not listed in the project plan
What should the project manager do?


A.
Stop work on the new task, initiate the change control process, and inform the customer.
B. Discuss the issue with the team member and stop the work.
C. Update the scope baseline and complete the task.
D. Update the project plan with the change and ask the client to communicate any future changes.

Correct Answer: A