Project Management Professional (PMP) Exam Practice – Question0890

A project to implement a new business improvement is initiated by the sponsor. The project manager has concerns regarding high-level requirements
What should the project manager do?


A.
Interview the stakeholders.
B. Organize focus groups.
C. Conduct brainstorming sessions.
D. Perform an assumption and constraint analysis.

Correct Answer: D