A multinational company with a cross-border project wants to implement new software that will impact several departments. The project manager needs to guarantee alignment of stakeholder expectations with the final product.
What should the project team develop?


A.
Project statement of work (SOW)
B. Stakeholder engagement plan
C. Stakeholders engagement assessment matrix
D. Risk breakdown structure (RBS)

Correct Answer: B