A project manager notices an unusually high rate of risks, but has limited resources to address them. To what should the project manager refer to determine risk priorities?


A.
Risk breakdown structure (RBS)
B. Risk probability and impact matrix
C. Risk management plan
D. Risk mitigation strategy

Correct Answer: D