A preventive action is approved by the change control board (CCB). What should the project manager do next?
A. Implement the action.
B. Add a contingency reserve for the risk.
C. Request the project sponsor's authorization.
D. Issue a change request.
A. Implement the action.
B. Add a contingency reserve for the risk.
C. Request the project sponsor's authorization.
D. Issue a change request.