A project manager notices that work started by the project team is misaligned with an industry regulation. The project manager recalls that this topic was previously discussed during a stakeholder meeting.
What should the project manager review?
A. Organizational process assets
B. Work performance data
C. Issue log
D. Project management plan
What should the project manager review?
A. Organizational process assets
B. Work performance data
C. Issue log
D. Project management plan