Project Management Professional (PMP) Exam Practice – Question0895

A project manager notices that work started by the project team is misaligned with an industry regulation. The project manager recalls that this topic was previously discussed during a stakeholder meeting.
What should the project manager review?


A.
Organizational process assets
B. Work performance data
C. Issue log
D. Project management plan

Correct Answer: A