Project Management Professional (PMP) Exam Practice – Question0897

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?


A.
Risk and uncertainty increase; the cost of changes increases.
B. Risk and uncertainty increase; the cost of changes decreases,
C. Risk and uncertainty decrease; the cost of changes increases.
D. Risk and uncertainty decrease; the cost of changes decreases.

Correct Answer: C