Project Management Professional (PMP) Exam Practice – Question0899 The Perform Quality Assurance process occurs in which Process Group? A. Executing B. Monitoring and Controlling C. Initiating D. Planning Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0898Project Management Professional (PMP) Exam Practice – Question0900