Project Management Professional (PMP) Exam Practice – Question0901

Which input provides suppliers with a clear set of goals, requirements, and outcomes?


A.
Procurement statement of work
B. Purchase order
C. Source selection criteria
D. Bidder conference

Correct Answer: A