Project Management Professional (PMP) Exam Practice – Question0904

During a projects execution phase, team members disagree about how to proceed with upcoming tasks due to intellectual property conflicts and non-disclosure agreements with external resources. What should the project manager do?


A.
Ask the team to agree to compromise and move on
B. Document it in the issue log
C. Escalate it to senior management
D. Work with the team to incorporate multiple viewpoints

Correct Answer: C