Project Management Professional (PMP) Exam Practice – Question0905

A project manager recently involved with constructing a hospital in country A is now managing the construction of an identical hospital in country B. Due to the projects similarities, a team member proposes adapting the lessons learned from country As project,
and proceeding without updating the lessons learned during construction in country B.

What should the project manager do?


A.
Ensure that lessons learned are updated during the construction in country B
B. Construct the hospital in country B using country As project management plan
C. Agree with the team member, and discuss the lessons learned with hospital management in country B
D. Document new lessons learned for country Bs hospital using industry benchmarks

Correct Answer: D