A project manager is receiving conflicting requirements from several stakeholders, all of which are ranked as high. What should the project manager do?
A. Perform a stakeholder analysis
B. Conduct personal interviews with stakeholders
C. Work with the project sponsor to resolve conflicts and work priorities
D. Execute an impact analysis of the requirements