Project Management Professional (PMP) Exam Practice – Question0907

A project team is geographically distributed across several countries. The team agrees to use one language while working on the project. Midway through the project, the project manager notices that the team is underperforming due to significant delays in
communication among team members.

What should the project manager evaluate first?


A.
Level of trust among team members
B. Degree of proficiency in the chosen language
C. Team members understanding of what is expected
D. Possession of required competencies by team members

Correct Answer: B