Project Management Professional (PMP) Exam Practice – Question0909

A customer expresses concern about delays after the implementation of an approved change. What corrective action should the project manager take?


A.
Add resources to address the customers concerns

B. Adjust the schedule baseline
C. Determine if the change was implemented correctly
D. Roll back the change

Correct Answer: B