Project Management Professional (PMP) Exam Practice – Question0912

A project is progressing, but stakeholders show little interest and supply minimal effort. To engage the stakeholders, what should the project manager do first?


A.
Ensure that the communications management plan is being followed
B. Ask management for assistance
C. Encourage other managers to influence the stakeholders
D. Document a risk detailing stakeholders lack of involvement and the impact on the project

Correct Answer: A