Project Management Professional (PMP) Exam Practice – Question0914

A project manager assumes an ongoing project with teams working across three continents. The previous project manager advises that participation in weekly status meetings has been low.
What should the new project manager do to find ways to resolve the problem?


A.
Review the kick-off meeting report to see if all teams participated
B. Check the resource breakdown structure (RBS) to determine if there are known team conflicts
C. Reference the requirements traceability matrix to see if all teams are required to attend
D. Determine if team time zones are listed in the communications management plan

Correct Answer: D