Project Management Professional (PMP) Exam Practice – Question0915

A customer requests minor changes to product specifications. The engineering manager claims that the man-hour cost of revising the documentation is far higher than the commercial value of the change itself. They suggest authorizing the change via email to the
project team.

What should the project manager do?


A.
Ask the engineering manager to issue a change request
B. Accept the engineering managers suggestion
C. Have the engineering manager obtain an opinion from the project management office (PMO)
D. Advise the engineering manager to revise the documentation

Correct Answer: C