Project Management Professional (PMP) Exam Practice – Question0921

What are the Project Procurement Management processes?


A.
Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Correct Answer: C