Project Management Professional (PMP) Exam Practice – Question0931

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:


A.
Start-to-start (SS).
B. Start-to-finish (SF).
C. Finish-to-start (FS).
D. Finish-to-finish (FF).

Correct Answer: C