Project Management Professional (PMP) Exam Practice – Question0936

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:


A.
Validate Scope.
B. Plan Scope Management.
C. Control Scope.
D. Define Scope.

Correct Answer: C