Project Management Professional (PMP) Exam Practice – Question0937 Which output is the approved version of the time-phased project budget? A. Resource calendar B. Scope baseline C. Trend analysis D. Cost baseline Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question0936Project Management Professional (PMP) Exam Practice – Question0938