Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
A. Level of control.
B. Communication channels.
C. Scope.
D. Strategic alignment.
A. Level of control.
B. Communication channels.
C. Scope.
D. Strategic alignment.