Project Management Professional (PMP) Exam Practice – Question0942

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:


A.
ends.
B. begins.
C. delays.

D. deviates.

Correct Answer: A