Project Management Professional (PMP) Exam Practice – Question0947

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?


A.
100
B. 120
C. 1,000
D. 1,200

Correct Answer: A