Project Management Professional (PMP) Exam Practice – Question0947 Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units? A. 100 B. 120 C. 1,000 D. 1,200 Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0946Project Management Professional (PMP) Exam Practice – Question0948