Project Management Professional (PMP) Exam Practice – Question0948

Perform Integrated Change Control is the process of:


A.
Reviewing, approving, and managing all change requests
B. Facilitating change management, manuals, or automation tools
C. Comparing actual results with planned results in order to expand or change a project
D. Documenting changes according to the change control system by the change control board

Correct Answer: A