Project Management Professional (PMP) Exam Practice – Question0955

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?


A.
0.8
B. 1
C. 1.25
D. 1.8

Correct Answer: C