Project Management Professional (PMP) Exam Practice – Question0958

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?


A.
0.83
B. 0.9
C. 1.11
D. 1.33

Correct Answer: C