The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
A. Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget
A. Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget