Which enterprise environmental factors may influence Plan Schedule Management?


A.
Cultural views regarding time schedules and professional and ethical behaviors
B. Historical information and change control procedures
C. Risk control procedures and the probability and impact matrix
D. Resource availability and organizational culture and structure

Correct Answer: D