Project Management Professional (PMP) Exam Practice – Question0974

Outputs of the Control Communications process include:


A.
expert judgment and change requests
B. work performance information and change requests
C. project management plan updates and work performance information
D. issue logs and organizational process assets updates

Correct Answer: B