Project Management Professional (PMP) Exam Practice – Question0975

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as
the:


A.
budget at completion (BAC)
B. earned value management (EVM)
C. to-complete performance index
D. cost performance index

Correct Answer: C