Project Management Professional (PMP) Exam Practice – Question0982 What is the term assigned to products or services having the same functional use but different technical characteristics? A. Scope B. Quality C. Specification D. Grade Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question0981Project Management Professional (PMP) Exam Practice – Question0983