Project Management Professional (PMP) Exam Practice – Question0992 Cost baseline is an output of which of the following processes? A. Control Costs B. Determine Budget C. Estimate Costs D. Estimate Activity Resources Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question0991Project Management Professional (PMP) Exam Practice – Question0993