Change requests are an output from which Project Integration Management process?
A. Direct and Manage Project Execution
B. Develop Project Management Plan
C. Close Project
D. Develop Project Charter
A. Direct and Manage Project Execution
B. Develop Project Management Plan
C. Close Project
D. Develop Project Charter