Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A. Estimate Costs
B. Estimate Activity Resources
C. Control Costs
D. Determine Budget
A. Estimate Costs
B. Estimate Activity Resources
C. Control Costs
D. Determine Budget