Project Management Professional (PMP) Exam Practice – Question1001 How is the schedule variance calculated using the earned value technique? A. EV less AC B. AC less PV C. EV less PV D. AC less EV Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question1000Project Management Professional (PMP) Exam Practice – Question1002