Project Management Professional (PMP) Exam Practice – Question1004

Which technique helps to determine the risks that have the most potential impact on a project?


A.
Cost risk simulation analysis
B. Expected monetary value analysis
C. Modeling and simulation
D. Sensitivity analysis

Correct Answer: D