In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
A. enterprise environmental factors.
B. organizational process assets.
C. project management plan,
D. project funding requirements.
A. enterprise environmental factors.
B. organizational process assets.
C. project management plan,
D. project funding requirements.