Project Management Professional (PMP) Exam Practice – Question1015

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?


A.
Perform Quality Control
B. Perform Quality Assurance
C. Plan Quality
D. Report Performance

Correct Answer: A