Project Management Professional (PMP) Exam Practice – Question1018

Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?


A.
Performance organizations
B. Schedule baselines
C. Work performance measurements
D. Change requests

Correct Answer: C