Project Management Professional (PMP) Exam Practice – Question1022

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost
performance index?


A.
0.8
B. 0.89
C. 1.13
D. 1.25

Correct Answer: A