Project Management Professional (PMP) Exam Practice – Question1027

The process to ensure that appropriate quality standards and operational definitions are used is:


A.
Plan Quality.
B. Perform Quality Assurance.
C. Perform Quality Control.
D. Total Quality Management.

Correct Answer: B