Project Management Professional (PMP) Exam Practice – Question1037

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?


A.
Estimate at completion
B. Cost performance
C. Schedule performance
D. To-complete performance

Correct Answer: D