Project Management Professional (PMP) Exam Practice – Question1039 The process improvement plan details the steps for analyzing processes to identify activities which enhance their: A. quality. B. value. C. technical performance. D. status. Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1038Project Management Professional (PMP) Exam Practice – Question1040